Rural water supply and sanitation improvement project (RWSSIP)

Funding Information
(USD)
Total Actual Commitment:
72,000,000 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
60,669,999 USD
Total Planned Disbursements:
0 USD
Unallocated Disbursements:
11,330,001 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
bpradhan@mof.gov.np
Project Modified By:
worldbank@amp.org
Project Created On:
10/19/2021
Created in workspace:
IECCD Workspace -Team
 
Identification
Project Title: 
Rural water supply and sanitation improvement project (RWSSIP) VALIDATED
ID: 
87238209024

IATI Identifier: 


Gender Marker: 
Neutral

Climate Change Relevance: 
Neutral

Status:  On-Going
Budget Head:  347 
Status Reason: 

 


Input: 

 


Outputs: 

Targeted people will be benefited by water supply,  hygiene and sanitation.


Outcome:

Improvement in quality of life, environmental conditions and increased  opportunities.

Improvement in rural livelihoods through rational,equitable and  sustainable use of water supplies,sanitation and hygiene in rural areas.


Impact: 

Improve health of rural people.

Improve quality of life.



Budget Type:
On Budget

Treasury Type:


Humanitarian Aid: No

Planning

Date of Agreement:  07-11-2014
Date of effectiveness:  11-10-2014
Proposed Start Date: 
Actual Start Date: 
Planned Completion Date:  06-30-2020
Location
[NEPAL] 100.0%

X

Map

Show Map
National Plan
[National Development Plan (NDP)]   [Social Development Policy]   [Drinking Water and Sanitation] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - URBAN DEVELOPMENT (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • International Development Association

Counterpart Ministry : 
  • Ministry of Urban Development 100.0 %

Executing Agency: 
  • Ministry of Urban Development 100.0 %

Implementing Agency: 
  • Rural Water Supply and Sanitation Fund Development Board 100.0 %
Funding
GON Fund
Location Transaction Date Amount
Federal NPR
Benificary Fund
Location Transaction Date Amount
Federal NPR
International Development Association
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 05-29-2014 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 50,000,000 USD
Actual Commitment 07-10-2014 Grant Aid Reimbursable No NORMAL CASE Project Support 22,000,000 USD
Sub Total Actual Commitment: 72,000,000 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 06-30-2015 Grant Aid Reimbursable No NORMAL CASE Project Support 2,120,000 USD
Actual Disbursement 06-30-2015 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 5,040,000 USD
Actual Disbursement 06-30-2016 Grant Aid Reimbursable No NORMAL CASE Project Support 670,000 USD
Actual Disbursement 06-30-2016 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 1,630,000 USD
Actual Disbursement 06-30-2017 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 9,300,571 USD
Actual Disbursement 06-30-2017 Grant Aid Reimbursable No NORMAL CASE Project Support 4,550,705 USD
Actual Disbursement 06-30-2018 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 11,416,480 USD
Actual Disbursement 06-30-2018 Grant Aid Reimbursable No NORMAL CASE Project Support 5,166,073 USD
Actual Disbursement 06-30-2019 Grant Aid Reimbursable No NORMAL CASE Project Support 3,286,793 USD
Actual Disbursement 06-30-2019 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 6,333,549 USD
Actual Disbursement 06-16-2020 Grant Aid Reimbursable No NORMAL CASE Project Support 3,707,979 USD
Actual Disbursement 06-16-2020 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 6,222,616 USD
Actual Disbursement 04-16-2021 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 290,000 USD
Actual Disbursement 07-01-2021 Grant Aid Reimbursable No NORMAL CASE Project Support 650,000 USD
Actual Disbursement 06-10-2022 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 285,233 USD
Sub Total Actual Disbursement: 60,669,999 USD
Sub Total Planned Disbursement: 0 USD
UNDISBURSED BALANCE: 11,330,001 USD
Progress Achieved

Progress Achieved: 

 


Key Problems: 

 


Steps Taken to solve the problem: 

 


Document

Open a PDF file of the doc attached Open.