Rural Access Programme Phase III

Funding Information
(USD)
Total Actual Commitment:
110,450,945 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
93,558,758 USD
Total Planned Disbursements:
14,991,079 USD
Unallocated Disbursements:
16,892,187 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
bpradhan@mof.gov.np
Project Modified By:
dfid@amp.org
Project Created On:
08/19/2021
Created in workspace:
DFID -Team
 
Identification
Project Title: 
Rural Access Programme Phase III VALIDATED
ID: 
872381433633

IATI Identifier: 


Gender Marker: 
Indirectly Supportive

Climate Change Relevance: 
Neutral

Status:  On-Going
Budget Head:  365810 
Status Reason: 
  • First phase out 2008
  • 2nd phase started from 2008 nov 14- 31 march 2013.
  • 2nd phase extended till september 2013.

Input: 
  • Maintenance and Upgradation of Roads.
  • Construction of new roads.
  • Economic Infrastructure.
  • Technical Assistance.
  • Results,evaluation and policy support.

Outputs: 
  • Employment opportunities will be created.
  • No of days of employment generated-7.5m days.
  • 600 kms of roads will be maintained, rehabilitated.
  • New roads will be contructed.

Outcome:
  • Improved income and resilience.
  • Sustainable access to markets and economic opportunities.
  • Income disparity will be reduced.

Impact: 
  • People almost 20000 (short term) will be employed.
  • more secure and sustainable livelihoods .
  • economic activities will be rife.


Budget Type:
On Budget

Treasury Type:


Humanitarian Aid: No

Planning

Date of Agreement:  03-11-2013
Date of effectiveness:  03-11-2013
Proposed Start Date:  01-31-2013
Actual Start Date:  05-31-2013
Planned Completion Date:  05-31-2023
Extension Date 1:  05-31-2013
Location
[ Karnali ] [Mugu (Gamgadhi)] 14.0%

[Seti ] [Bajura (Martadi)] 14.0%

[ Karnali ] [Kalikot (Kalikot)] 15.0%

[Bheri] [Dailekh (Dullu)] 14.0%

[Seti ] [Achham (Mangalsen)] 15.0%

[ Karnali ] [Humla (Simikot)] 14.0%

[ Karnali ] [Jumla (Jumla Khalanga)] 14.0%

X

Map

Show Map
National Plan
[National Development Plan (NDP)]   [Infrastructure Development Policy]   [Road and Other Transports] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - LOCAL DEVELOPMENT (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • Department for International Development

Counterpart Ministry : 
  • Ministry of Federal Affairs and General Administration 100.0 %

Executing Agency: 
  • Ministry of Finance 100.0 %

Implementing Agency: 
  • Department of Local Infrastructure Development and Agricultural Roads 100.0 %
Funding
GON Fund
Location Transaction Date Amount
Federal NPR
Benificary Fund
Location Transaction Date Amount
Federal NPR
Department for International Development
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 05-31-2013 Grant Aid Direct Payment No NORMAL CASE Project Support 110,450,945 USD
Sub Total Actual Commitment: 110,450,945 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 03-31-2013 Grant Aid Direct Payment No NORMAL CASE Project Support 15,113,032 USD
Actual Disbursement 03-31-2014 Grant Aid Direct Payment No NORMAL CASE Project Support 12,583,852 USD
Actual Disbursement 03-31-2015 Grant Aid Direct Payment No NORMAL CASE Project Support 15,416,166 USD
Actual Disbursement 07-31-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 503,790 USD
Actual Disbursement 08-31-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 1,113,500 USD
Actual Disbursement 09-30-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 1,028,208 USD
Actual Disbursement 10-31-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 1,067,202 USD
Actual Disbursement 11-30-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 944,055 USD
Actual Disbursement 12-31-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 1,837,299 USD
Actual Disbursement 01-31-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 1,052,471 USD
Actual Disbursement 02-28-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 1,106,637 USD
Actual Disbursement 03-31-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 1,209,780 USD
Actual Disbursement 04-30-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 49,022 USD
Actual Disbursement 05-31-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 1,052,131 USD
Actual Disbursement 06-30-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 1,056,803 USD
Actual Disbursement 07-31-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 582,037 USD
Actual Disbursement 08-31-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 717,187 USD
Actual Disbursement 09-30-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 777,790 USD
Actual Disbursement 10-31-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 1,237,457 USD
Actual Disbursement 11-30-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 1,345,443 USD
Actual Disbursement 12-31-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 1,051,365 USD
Actual Disbursement 01-31-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 1,423,304 USD
Actual Disbursement 02-28-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 1,234,774 USD
Actual Disbursement 03-31-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 785,306 USD
Actual Disbursement 03-31-2019 Grant Aid Direct Payment No NORMAL CASE Project Support 13,104,128 USD
Actual Disbursement 07-31-2019 Grant Aid Direct Payment No NORMAL CASE Project Support 2,320,350 USD
Actual Disbursement 06-30-2020 Grant Aid Direct Payment No NORMAL CASE Project Support 3,691,323 USD
Actual Disbursement 06-30-2021 Grant Aid Direct Payment No NORMAL CASE Project Support 4,916,459 USD
Actual Disbursement 06-30-2022 Grant Aid Direct Payment No NORMAL CASE Project Support 5,237,885 USD
Sub Total Actual Disbursement: 93,558,758 USD
Planned Disbursement 03-31-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 14,991,079 USD
Sub Total Planned Disbursement: 14,991,079 USD
UNDISBURSED BALANCE: 16,892,187 USD
Progress Achieved

Progress Achieved: 

 


Key Problems: 

 


Steps Taken to solve the problem: 

 


Document

Open a PDF file of the doc attached Open.