Mugling Pokhara Highway Improvemant Project

Funding Information
(USD)
Total Actual Commitment:
195,000,000 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
19,840,546 USD
Total Planned Disbursements:
0 USD
Unallocated Disbursements:
175,159,454 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
drdahal@mof.gov.np
Project Modified By:

Project Created On:
08/18/2021
Created in workspace:
IECCD Workspace -Team
 
Identification
Project Title: 
Mugling Pokhara Highway Improvemant Project VALIDATED
ID: 
87238117723820

IATI Identifier: 


Gender Marker: 
Neutral

Climate Change Relevance: 
Neutral

Status:  On-Going
Budget Head: 
Status Reason: 

 


Input: 

Rehabilitation and upgrding about 81 km of road between Abukhaireni to Pokhara to a 4-lane standard; and

improving awareness of communities and capacity of the government on road safety, disaster risk reduction and project implementation capacity


Outputs: 

Intelligent traffic management and information system for road safety developed


Outcome:

Landslide monitoring and management system for disaster risk reduction developed.

Procurement and contract management capacity enhanced.


Impact: 

 



Budget Type:
On Budget

Treasury Type:
On-treasury

Humanitarian Aid: No

Planning

Date of Agreement:  12-10-2019
Date of effectiveness: 
Proposed Start Date: 
Actual Start Date: 
Planned Completion Date:  01-31-2025
Location
[Gandaki Pradesh] [Kaski (Pokhara)] 50.0%

[Gandaki Pradesh] [Tanahu (Damauli)] 50.0%

X

Map

Show Map
National Plan
[National Development Plan (NDP)]   [Infrastructure Development Policy]   [Road and Other Transports] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - ROAD TRANSPORTATION (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • Asian Development Bank

Counterpart Ministry : 
  • Ministry of Physical Infrastructure and Transport 100.0 %

Executing Agency: 
  • Ministry of Physical Infrastructure and Transport 100.0 %

Implementing Agency: 
  • Ministry of Physical Infrastructure and Transportation 100.0 %
Funding
GON Fund
Location Transaction Date Amount
Federal NPR
Benificary Fund
Location Transaction Date Amount
Federal NPR
Asian Development Bank
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 09-27-2019 Concessional Loan Assistance Direct Payment No NORMAL CASE Project Support 195,000,000 USD
Sub Total Actual Commitment: 195,000,000 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 03-31-2021 Concessional Loan Assistance Direct Payment No NORMAL CASE Project Support 9,750,000 USD
Actual Disbursement 07-15-2021 Concessional Loan Assistance Direct Payment No NORMAL CASE Project Support 6,229 USD
Actual Disbursement 11-15-2021 Concessional Loan Assistance Direct Payment No NORMAL CASE Project Support 2,644,528 USD
Actual Disbursement 03-15-2022 Concessional Loan Assistance Direct Payment No NORMAL CASE Project Support 6,072,226 USD
Actual Disbursement 07-15-2022 Concessional Loan Assistance Direct Payment No NORMAL CASE Project Support 1,367,563 USD
Sub Total Actual Disbursement: 19,840,546 USD
Sub Total Planned Disbursement: 0 USD
UNDISBURSED BALANCE: 175,159,454 USD
Progress Achieved

Progress Achieved: 

 


Key Problems: 

 


Steps Taken to solve the problem: 

 


Document