Reconstruction and Rehabilitation of Schools and Health Facilities in Makwanpur District

Funding Information
(USD)
Total Actual Commitment:
42,454,952 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
10,779,731 USD
Total Planned Disbursements:
33,846,048 USD
Unallocated Disbursements:
31,675,221 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
usaid@amp.org
Project Modified By:
usaid@amp.org
Project Created On:
08/13/2021
Created in workspace:
USAID -Team
 
Identification
Project Title: 
Reconstruction and Rehabilitation of Schools and Health Facilities in Makwanpur District VALIDATED
ID: 
872388122762

IATI Identifier: 


Gender Marker: 
Indirectly Supportive

Climate Change Relevance: 
Neutral

Status:  On-Going
Budget Head: 
Status Reason: 

 


Input: 

 


Outputs: 

 


Outcome:

 


Impact: 

 



Budget Type:
Off Budget

Treasury Type:


Humanitarian Aid: Yes

Planning

Date of Agreement:  02-11-2019
Date of effectiveness: 
Proposed Start Date: 
Actual Start Date: 
Planned Completion Date:  09-15-2020
Location
[Bagmati Pradesh] [Makwanpur (Hetauda)] 100.0%

X

Map

Show Map
National Plan
[National Development Plan (NDP)]   [Social Development Policy]   [Social Protection] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - EARTHQUAKE RECONSTRUCTION (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • U.S. Agency for International Development

Counterpart Ministry : 
  • Nepal Reconstruction Authority 100.0 %

Executing Agency: 
  • U.S. Agency for International Development 100.0 %

Implementing Agency: 
  • U.S. Agency for International Development 100.0 %
Funding
Japan International Cooperation Agency
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 02-15-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 42,454,952 USD
Sub Total Actual Commitment: 42,454,952 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 07-14-2020 Grant Aid Direct Payment No NORMAL CASE Project Support 10,779,731 USD
Sub Total Actual Disbursement: 10,779,731 USD
Planned Disbursement 03-31-2020 Grant Aid Direct Payment No NORMAL CASE Project Support 11,282,016 USD
Planned Disbursement 03-31-2021 Grant Aid Direct Payment No NORMAL CASE Project Support 11,282,016 USD
Planned Disbursement 03-31-2022 Grant Aid Direct Payment No NORMAL CASE Project Support 11,282,016 USD
Sub Total Planned Disbursement: 33,846,048 USD
UNDISBURSED BALANCE: 31,675,221 USD
Progress Achieved

Progress Achieved: 

 


Key Problems: 

 


Steps Taken to solve the problem: 

 


Document

Open a PDF file of the doc attached Open.