TA - 8910, Support for project implementation of the Nepal Earthquake Rehabilation

Funding Information
(USD)
Total Actual Commitment:
2,100,000 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
2,459,883 USD
Total Planned Disbursements:
0 USD
Unallocated Disbursements:
-359,883 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
adb@amp.org
Project Modified By:
bpradhan@mof.gov.np
Project Created On:
04/13/2021
Created in workspace:
ADB -Team
 
Identification
Project Title: 
TA - 8910, Support for project implementation of the Nepal Earthquake Rehabilation VALIDATED
ID: 
872387915315

IATI Identifier: 


Gender Marker: 
Neutral

Climate Change Relevance: 
Relevant

Status:  On-Going
Budget Head: 
Status Reason: 

 


Input: 

 


Outputs: 

 


Outcome:

 


Impact: 

 



Budget Type:
Off Budget

Treasury Type:


Humanitarian Aid: Yes

Planning

Date of Agreement:  07-26-2015
Date of effectiveness:  07-26-2015
Proposed Start Date: 
Actual Start Date: 
Planned Completion Date:  06-30-2018
Location
[NEPAL] 100.0%

X

Map

Show Map
National Plan
Sectors

PRIMARY SECTORS
Nepal Sector Classification - EDUCATION (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • Asian Development Bank

Counterpart Ministry : 
  • Ministry of Education 100.0 %

Executing Agency: 
  • Ministry of Education 100.0 %

Implementing Agency: 
  • Ministry of Education 100.0 %
Funding
Asian Development Bank
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 07-26-2015 Technical Assistance (Standalone) Direct Payment Yes NORMAL CASE Humanitarian Assistance 2,100,000 USD
Sub Total Actual Commitment: 2,100,000 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 03-15-2016 Technical Assistance (Standalone) Direct Payment Yes NORMAL CASE Humanitarian Assistance 46,736 USD
Actual Disbursement 07-15-2016 Technical Assistance (Standalone) Direct Payment Yes NORMAL CASE Humanitarian Assistance 87,626 USD
Actual Disbursement 11-15-2016 Technical Assistance (Standalone) Direct Payment Yes NORMAL CASE Humanitarian Assistance 129,488 USD
Actual Disbursement 03-15-2017 Technical Assistance (Standalone) Direct Payment Yes NORMAL CASE Humanitarian Assistance 152,839 USD
Actual Disbursement 07-05-2017 Technical Assistance (Standalone) Direct Payment Yes NORMAL CASE Humanitarian Assistance 214,021 USD
Actual Disbursement 11-15-2017 Technical Assistance (Standalone) Direct Payment Yes NORMAL CASE Humanitarian Assistance 158,186 USD
Actual Disbursement 03-15-2018 Technical Assistance (Standalone) Direct Payment Yes NORMAL CASE Humanitarian Assistance 306,584 USD
Actual Disbursement 07-15-2018 Technical Assistance (Standalone) Direct Payment Yes NORMAL CASE Humanitarian Assistance 418,442 USD
Actual Disbursement 11-15-2018 Technical Assistance (Standalone) Direct Payment Yes NORMAL CASE Humanitarian Assistance 297,542 USD
Actual Disbursement 03-15-2019 Technical Assistance (Standalone) Direct Payment Yes NORMAL CASE Humanitarian Assistance 312,203 USD
Actual Disbursement 07-15-2019 Technical Assistance (Standalone) Direct Payment Yes NORMAL CASE Humanitarian Assistance 336,216 USD
Sub Total Actual Disbursement: 2,459,883 USD
Sub Total Planned Disbursement: 0 USD
UNDISBURSED BALANCE: -359,883 USD
Progress Achieved

Progress Achieved: 

 


Key Problems: 

 


Steps Taken to solve the problem: 

 


Document

Open a PDF file of the doc attached Open.