Operation and Maintenance of Sindhuli Road - Phase II

Funding Information
(USD)
Total Actual Commitment:
2,803,372 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
49,747 USD
Total Planned Disbursements:
582,904 USD
Unallocated Disbursements:
2,753,624 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
japan@amp.org
Project Modified By:
bpradhan@mof.gov.np
Project Created On:
12/29/2020
Created in workspace:
Japan -Team
 
Identification
Project Title: 
Operation and Maintenance of Sindhuli Road - Phase II VALIDATED
ID: 
872389222997

IATI Identifier: 


Gender Marker: 
Neutral

Climate Change Relevance: 
Relevant

Status:  On-Going
Budget Head: 
Status Reason: 

 


Input: 

Experts

Training


Outputs: 

1. Improved capacity to operate and maintain Sindhuli Road

2. Enhanced capacity to take measures for traffic safety

3. Enhanced capacity to restore damaged causeways of Sindhuli Road


Outcome:

Strengthened overall operation and maintenance system of Sindhuli Road


Impact: 

Maintained safe and smooth road traffic along Sindhuli Road



Budget Type:
Off Budget

Treasury Type:


Humanitarian Aid: No

Planning

Date of Agreement:  04-11-2018
Date of effectiveness:  04-11-2018
Proposed Start Date:  04-15-2018
Actual Start Date:  04-15-2018
Planned Completion Date:  03-31-2021
Extension Date 1:  04-15-2018
Location
[Janakpur] [Sindhuli (Sindhuli Madhi)] 33.0%

[Bagmati] [Kavrepalanchok (Dhulikhel)] 34.0%

[Janakpur] [Mahottari (Jaleswor)] 33.0%

X

Map

Show Map
National Plan
[National Development Plan (NDP)]   [Infrastructure Development Policy]   [Road and Other Transports] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - ROAD TRANSPORTATION (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • Japan International Cooperation Agency

Counterpart Ministry : 
  • Ministry of Irrigation 50.0 %
  • Ministry of Physical Infrastructure and Transport 50.0 %

Executing Agency: 
  • Department of Irrigation 50.0 %
  • Department of Road 50.0 %

Implementing Agency: 
  • Japan International Cooperation Agency 100.0 %
Funding
Japan International Cooperation Agency
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 04-11-2018 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Project Support 2,803,372 USD
Sub Total Actual Commitment: 2,803,372 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 03-31-2020 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Project Support 49,747 USD
Sub Total Actual Disbursement: 49,747 USD
Planned Disbursement 03-31-2020 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Project Support 582,904 USD
Sub Total Planned Disbursement: 582,904 USD
UNDISBURSED BALANCE: 2,753,624 USD
Progress Achieved

Progress Achieved: 

 


Key Problems: 

 


Steps Taken to solve the problem: 

 


Document

Open a PDF file of the doc attached Open.