Budhi Ganga Hydropower Project

Funding Information
(USD)
Total Actual Commitment:
47,693,686 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
5,047,518 USD
Total Planned Disbursements:
0 USD
Unallocated Disbursements:
42,646,168 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
bpradhan@mof.gov.np
Project Modified By:
atl@mof.gov.np
Project Created On:
08/16/2020
Created in workspace:
IECCD Workspace -Team
 
Identification
Project Title: 
Budhi Ganga Hydropower Project VALIDATED
ID: 
8723823100

IATI Identifier: 


Gender Marker: 
Neutral

Climate Change Relevance: 
Neutral

Status:  On-Going
Budget Head:  308112 
Status Reason: 

Budhi Ganga Hydropower Project as an important but small scale project primarily targetted for the regional development in the far development region. Lacated in the Sanfebagar of Achham District this project is in the pipeline since the process of acquiring the loan from the proposed donor Kuwait Fund for Arab Economic Devlopment.


Input: 
  • Headworks comprising of a diversion weir and desanding facilities
  • Waterways consisting of a 5.5 km long abd 3.9 m dia headrace tunnel. A surge tank, a 219 m long and 3.5 m diameter penstock and a 100 m long tailrace open channel
  • Surface powerhouse with an installed capacity of 20 MW (2x10 MW)
  • A 132 kv and 88.6 km long transmission line to Lumki substation
  • Acess road of approx 3.5 km length

Outputs: 

The Budhi Ganga Hydropower project lies in Achham District in FWDR of Nepal. This is a Medium Hydropower Study project of Nepal Electricity Authority (NEA) which is designed to meet six hours of peak load.


Outcome:

 Generation of 20 MW hydroelectricity.


Impact: 

Contributed to the electrification of the nation.

 



Budget Type:
On Budget

Treasury Type:


Humanitarian Aid: No

Planning

Date of Agreement:  03-22-2013
Date of effectiveness:  03-22-2013
Proposed Start Date:  03-22-2013
Actual Start Date:  03-22-2013
Planned Completion Date:  03-02-2018
Location
[Seti ] [Achham (Mangalsen)] 100.0%

X

Map

Show Map
National Plan
[Infrastructure Development Policy]   [Water Resources]   [Hydro Electricity] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - ELECTRICITY (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • Saudi Development Fund
  • Kuwait fund for Arab Economic development

Counterpart Ministry : 
  • Ministry of Energy 100.0 %

Executing Agency: 
  • Department of Electricity Development 100.0 %

Implementing Agency: 
  • Nepal Electricity Authority 100.0 %
Funding
GON Fund
Location Transaction Date Amount
Federal NPR
Benificary Fund
Location Transaction Date Amount
Federal NPR
Saudi Development Fund
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 06-18-2014 Concessional Loan Assistance Cash No NORMAL CASE Project Support 29,693,686 USD
Sub Total Actual Commitment: 29,693,686 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 07-17-2015 Concessional Loan Assistance Cash No NORMAL CASE Project Support 190,018 USD
Actual Disbursement 06-30-2017 Concessional Loan Assistance Cash No NORMAL CASE Project Support 583,624 USD
Actual Disbursement 06-30-2018 Concessional Loan Assistance Reimbursable No NORMAL CASE Program Based Support 163,451 USD
Actual Disbursement 06-30-2019 Concessional Loan Assistance Reimbursable No NORMAL CASE Program Based Support 568,013 USD
Actual Disbursement 06-30-2021 Concessional Loan Assistance Reimbursable No NORMAL CASE Program Based Support 22,364 USD
Actual Disbursement 06-30-2022 Concessional Loan Assistance Reimbursable No NORMAL CASE Program Based Support 116,173 USD
Actual Disbursement 06-30-2023 Concessional Loan Assistance Reimbursable No NORMAL CASE Program Based Support 170,374 USD
Sub Total Actual Disbursement: 1,814,016 USD
Sub Total Planned Disbursement: 0 USD
UNDISBURSED BALANCE: 27,879,670 USD
Kuwait fund for Arab Economic development
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 03-22-2013 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 18,000,000 USD
Sub Total Actual Commitment: 18,000,000 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 07-17-2015 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 541,771 USD
Actual Disbursement 06-30-2017 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 150,296 USD
Actual Disbursement 06-30-2018 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 376,552 USD
Actual Disbursement 06-30-2019 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 1,954,339 USD
Actual Disbursement 06-30-2020 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 210,544 USD
Sub Total Actual Disbursement: 3,233,502 USD
Sub Total Planned Disbursement: 0 USD
UNDISBURSED BALANCE: 14,766,498 USD
Progress Achieved

Progress Achieved: 


Key Problems: 


Steps Taken to solve the problem: 


Document