Nepal-India Regional Trade and Transport Project

Funding Information
(USD)
Total Actual Commitment:
100,610,400 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
58,529,560 USD
Total Planned Disbursements:
0 USD
Unallocated Disbursements:
42,080,840 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
bpradhan@mof.gov.np
Project Modified By:
bpradhan@mof.gov.np
Project Created On:
08/03/2020
Created in workspace:
IECCD Workspace -Team
 
Identification
Project Title: 
Nepal-India Regional Trade and Transport Project VALIDATED
ID: 
872383506292

IATI Identifier: 


Gender Marker: 
Indirectly Supportive

Climate Change Relevance: 
Neutral

Status:  On-Going
Budget Head:  330108 337330 
Status Reason: 

 


Input: 

 


Outputs: 

to decrease  transport  time  and logistics  costs  for bilateral trade between Nepal and  India and transit trade  along  the  Kathmandu -Kolkata  corridor for  the benifit of  traders by reducing  key  infrastructure bottleneck in Nepal and by  supporting  the adption  of modern  approaches to border management.


Outcome:

 


Impact: 

 



Budget Type:
On Budget

Treasury Type:


Humanitarian Aid: No

Planning

Date of Agreement:  07-11-2013
Date of effectiveness:  09-10-2013
Proposed Start Date:  07-11-2013
Actual Start Date:  07-11-2013
Planned Completion Date:  12-31-2019
Extension Date 1:  07-11-2013
Location
[NEPAL] 100.0%

X

Map

Show Map
National Plan
[National Development Plan (NDP)]   [Macroeconomic Policy and Economic Development Policy]   [Transport Management] 50.0%
[National Development Plan (NDP)]   [Macroeconomic Policy and Economic Development Policy]   [Trade] 50.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - COMMERCE (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • International Development Association

Counterpart Ministry : 
  • Ministry of Physical Infrastructure and Transportation 50.0 %
  • Ministry of Supplies 50.0 %

Executing Agency: 
  • International Development Association 100.0 %

Implementing Agency: 
  • Ministry of Physical Infrastructure and Transportation 50.0 %
  • Ministry of Supplies 50.0 %
Funding
GON Fund
Location Transaction Date Amount
Federal NPR
Benificary Fund
Location Transaction Date Amount
Federal NPR
International Development Association
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 07-11-2013 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 70,136,322 USD
Actual Commitment 07-11-2013 Grant Aid Reimbursable No NORMAL CASE Project Support 30,474,079 USD
Sub Total Actual Commitment: 100,610,400 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 06-30-2014 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 6,000,000 USD
Actual Disbursement 06-30-2014 Grant Aid Reimbursable No NORMAL CASE Project Support 2,000,000 USD
Actual Disbursement 06-30-2015 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 2,820,000 USD
Actual Disbursement 06-30-2015 Grant Aid Reimbursable No NORMAL CASE Project Support 420,000 USD
Actual Disbursement 06-30-2016 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 7,110,000 USD
Actual Disbursement 06-30-2016 Grant Aid Reimbursable No NORMAL CASE Project Support 620,000 USD
Actual Disbursement 02-27-2017 Grant Aid Reimbursable No NORMAL CASE Project Support 397,584 USD
Actual Disbursement 05-04-2017 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 5,157,178 USD
Actual Disbursement 06-30-2018 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 13,986,105 USD
Actual Disbursement 06-30-2018 Grant Aid Reimbursable No NORMAL CASE Project Support 1,673,592 USD
Actual Disbursement 06-30-2019 Grant Aid Reimbursable No NORMAL CASE Project Support 1,047,093 USD
Actual Disbursement 06-30-2019 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 6,550,261 USD
Actual Disbursement 03-12-2020 Grant Aid Reimbursable No NORMAL CASE Project Support 350,533 USD
Actual Disbursement 06-30-2020 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 10,397,214 USD
Sub Total Actual Disbursement: 58,529,560 USD
Sub Total Planned Disbursement: 0 USD
UNDISBURSED BALANCE: 42,080,840 USD
Progress Achieved

Progress Achieved: 


Key Problems: 


Steps Taken to solve the problem: 


Document

Open a PDF file of the doc attached Open.