NPL-17/0015 Advancing Hydropower Development in Nepal

Funding Information
(USD)
Total Actual Commitment:
5,264,408 USD
Total Planned Commitment:
3,993,658 USD
Total Actual Disbursements:
3,513,802 USD
Total Planned Disbursements:
0 USD
Unallocated Disbursements:
1,750,606 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
norway@amp.org
Project Modified By:
norway@amp.org
Project Created On:
07/13/2020
Created in workspace:
Norway -Team
 
Identification
Project Title: 
NPL-17/0015 Advancing Hydropower Development in Nepal VALIDATED
ID: 
872389621786

IATI Identifier: 


Gender Marker: 
Indirectly Supportive

Climate Change Relevance: 
Relevant

Status:  On-Going
Budget Head: 
Status Reason: 

 


Input: 

 


Outputs: 

 


Outcome:

-Improved development and implementation of regulatory frameworks for the hydropower sector

-Enhance ability of the private sector to invest in hydropower projects

-Successful demonistration of a PPP hydropower project


Impact: 

 



Budget Type:
Off Budget

Treasury Type:


Humanitarian Aid: No

Planning

Date of Agreement:  12-06-2018
Date of effectiveness:  12-06-2018
Proposed Start Date:  12-06-2018
Actual Start Date:  12-06-2018
Planned Completion Date:  06-30-2022
Extension Date 1:  12-06-2018
Location
[NEPAL] 100.0%

X

Map

Show Map
National Plan
[Infrastructure Development Policy]   [Water Resources]   [Hydro Electricity] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - ENERGY (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • Norway

Counterpart Ministry : 
  • Ministry of Energy 100.0 %

Executing Agency: 
  • International Finance Cooperation 100.0 %

Implementing Agency: 
  • Ministry of Energy 100.0 %
Funding
Norway
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 12-07-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 5,264,408 USD
Sub Total Actual Commitment: 5,264,408 USD
Planned Commitment 04-02-2019 Grant Aid Direct Payment No NORMAL CASE Project Support 2,344,963 USD
Planned Commitment 04-02-2020 Grant Aid Direct Payment No NORMAL CASE Project Support 1,099,130 USD
Planned Commitment 04-05-2021 Grant Aid Direct Payment No NORMAL CASE Project Support 549,565 USD
Sub Total Planned Commitment: 3,993,658 USD
Actual Disbursement 12-07-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 2,339,737 USD
Actual Disbursement 06-28-2019 Grant Aid Direct Payment No NORMAL CASE Project Support 1,174,065 USD
Sub Total Actual Disbursement: 3,513,802 USD
Sub Total Planned Disbursement: 0 USD
UNDISBURSED BALANCE: 1,750,606 USD
Progress Achieved

Progress Achieved: 


Key Problems: 


Steps Taken to solve the problem: 


Document