Small Irrigation Programme (SIP)

Funding Information
(USD)
Total Actual Commitment:
18,811,584 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
18,236,810 USD
Total Planned Disbursements:
14,409,045 USD
Unallocated Disbursements:
574,774 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
bpradhan@mof.gov.np
Project Modified By:

Project Created On:
06/20/2020
Created in workspace:
IECCD Workspace -Team
 
Identification
Project Title: 
Small Irrigation Programme (SIP) VALIDATED
ID: 
8723863211897

IATI Identifier: 


Gender Marker: 
Neutral

Climate Change Relevance: 
Neutral

Status:  On-Going
Budget Head: 
Status Reason: 

 


Input: 

small irrigation system is to be build in 9 districts of Ramechhap, Okhaldhunga, Khotang, Sindhuli, Udaypur, Achham, Dailekh, Kalikot and Jajarkot.


Outputs: 
  • 15,000 ha of irrigated areas are rehabilitated or newly builg. Approximately 1800 gravity irrigation schemes, stroage/pond irrigation schemes and other non-conventional irrigation developments are constructed or rehabilited.
  • Water user Associations (WUAs) strengthen their capacity to manage irrigation  systems in a socially inclusive, sustainable and equitable manner.

Outcome:

Small farmers especially from disadvantaged groups increase their productivity by managing and maintaining farmers managed irrigation (FMIS)


Impact: 

Rural poor especially the disadvantaged groups (DAGs) increase their agriculture income by40% in the areas of intervention and reduction of poverty by 10% (from 25% to 22.5%)



Budget Type:
On Budget

Treasury Type:
Off-treasury

Humanitarian Aid: No

Planning

Date of Agreement:  01-10-2015
Date of effectiveness:  01-10-2015
Proposed Start Date: 
Actual Start Date: 
Planned Completion Date:  01-28-2019
Location
[Sagarmatha ] [Okhaldhunga (Okhaldhunga)] 11.0%

[Sagarmatha ] [Khotang (Diktel)] 11.0%

[Janakpur] [Ramechhap (Manthali)] 11.0%

[Bheri] [Jajarkot (Khalanga)] 11.0%

[Bheri] [Dailekh (Dullu)] 11.0%

[Sagarmatha ] [Udayapur (Gaighat)] 11.0%

[Seti ] [Achham (Mangalsen)] 11.0%

[ Karnali ] [Kalikot (Kalikot)] 12.0%

[Janakpur] [Sindhuli (Sindhuli Madhi)] 11.0%

X

Map

Show Map
National Plan
[National Development Plan (NDP)]   [Infrastructure Development Policy]   [Rural Infrastructure] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - LOCAL DEVELOPMENT (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • Swiss Agency for Development and Cooperation

Counterpart Ministry : 
  • Ministry of Federal Affairs and General Administration 100.0 %

Executing Agency: 
  • Swiss Agency for Development and Cooperation 100.0 %

Implementing Agency: 
  • Department of Local Infrastructure Development and Agricultural Roads 100.0 %
Funding
GON Fund
Location Transaction Date Amount
Federal NPR
Benificary Fund
Location Transaction Date Amount
Federal NPR
Swiss Agency for Development and Cooperation
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 02-11-2015 Grant Aid Direct Payment No NORMAL CASE Project Support 17,025,953 USD
Actual Commitment 01-14-2019 Grant Aid Direct Payment No NORMAL CASE Project Support 1,785,631 USD
Sub Total Actual Commitment: 18,811,584 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 03-05-2015 Grant Aid Direct Payment No NORMAL CASE Project Support 2,512,327 USD
Actual Disbursement 12-07-2015 Grant Aid Direct Payment No NORMAL CASE Project Support 2,003,676 USD
Actual Disbursement 08-24-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 2,185,380 USD
Actual Disbursement 11-24-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 1,481,968 USD
Actual Disbursement 12-16-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 67,952 USD
Actual Disbursement 01-31-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 39,152 USD
Actual Disbursement 06-30-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 1,039,201 USD
Actual Disbursement 12-15-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 2,128,573 USD
Actual Disbursement 02-27-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 5,227 USD
Actual Disbursement 07-17-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 2,004,104 USD
Actual Disbursement 12-12-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 1,618,634 USD
Actual Disbursement 06-05-2019 Grant Aid Direct Payment No NORMAL CASE Project Support 1,508,857 USD
Actual Disbursement 11-26-2019 Grant Aid Direct Payment No NORMAL CASE Project Support 1,638,229 USD
Actual Disbursement 01-14-2020 Grant Aid Direct Payment No NORMAL CASE Project Support 3,530 USD
Sub Total Actual Disbursement: 18,236,810 USD
Planned Disbursement 12-31-2015 Grant Aid Direct Payment No NORMAL CASE Project Support 4,546,606 USD
Planned Disbursement 12-31-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 3,533,625 USD
Planned Disbursement 12-31-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 3,177,089 USD
Planned Disbursement 09-15-2019 Grant Aid Direct Payment No NORMAL CASE Project Support 3,151,724 USD
Sub Total Planned Disbursement: 14,409,045 USD
UNDISBURSED BALANCE: 574,774 USD
Progress Achieved

Progress Achieved: 


Key Problems: 


Steps Taken to solve the problem: 


Document

Open a PDF file of the doc attached Open.