Decentralized Rural Infrastructure and Livelihood Project (DRILP) Phase III

Funding Information
(USD)
Total Actual Commitment:
5,727,356 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
5,561,619 USD
Total Planned Disbursements:
6,412,161 USD
Unallocated Disbursements:
165,737 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
bpradhan@mof.gov.np
Project Modified By:

Project Created On:
01/28/2020
Created in workspace:
IECCD Workspace -Team
 
Identification
Project Title: 
Decentralized Rural Infrastructure and Livelihood Project (DRILP) Phase III VALIDATED
ID: 
8723863213928

IATI Identifier: 


Gender Marker: 
Neutral

Climate Change Relevance: 
Neutral

Status:  On-Going
Budget Head: 
Status Reason: 

A Technical Assistance to Government of Nepal in Implementation of Emergency Earthquake Assistance Project Funded by Asian Development Bank


Input: 

to contribute towards accelerated economic and social recovery in Nepal's earthquake affected districts


Outputs: 
  1. Road trails and bridges are rehabilitated and/or reconstructed.
  2. Disaster preparedness and management practices strengthened.

Outcome:

Critical economic and social services resumed for the affected population with operation of disaster resilient local roads and trails in the 12 affected districts


Impact: 
  • 450 kms of local roads in the District Core Road Network (DCRN) rehabilitated and or/ reconstructed. 200 kms of trails in Gorkha and Dolakha districts will also be rehabilitated and/or reconstructed through SDC's own funds.


Budget Type:
On Budget

Treasury Type:
Off-treasury

Humanitarian Aid: No

Planning

Date of Agreement: 
Date of effectiveness:  01-01-2016
Proposed Start Date: 
Actual Start Date: 
Planned Completion Date:  01-31-2019
Location
[Bagmati] [Bhaktapur (Bhaktapur)] 8.0%

[Bagmati] [Kathmandu (Kathmandu)] 8.0%

[Bagmati] [Lalitpur (Patan)] 8.0%

[Bagmati] [Kavrepalanchok (Dhulikhel)] 9.0%

[ Narayani ] [Chitwan (Bharatpur)] 9.0%

[Janakpur] [Sindhuli (Sindhuli Madhi)] 8.0%

[Gandaki] [Lamjung (Bensi Sahar)] 8.0%

[Janakpur] [Dholkha (Charikot)] 9.0%

[Janakpur] [Ramechhap (Manthali)] 9.0%

[Sagarmatha ] [Okhaldhunga (Okhaldhunga)] 8.0%

[Sagarmatha ] [Solukhumbu (Salleri)] 8.0%

[Gandaki] [Gorkha (Gorkha)] 8.0%

X

Map

Show Map
National Plan
[National Development Plan (NDP)]   [Infrastructure Development Policy]   [Road and Other Transports] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - LOCAL DEVELOPMENT (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • Swiss Agency for Development and Cooperation

Counterpart Ministry : 
  • Ministry of Federal Affairs and Local Development 100.0 %

Executing Agency: 
  • Ministry of Federal Affairs and Local Development 100.0 %

Implementing Agency: 
  • Department of Local Infrastructure Development and Agricultural Roads 100.0 %
Funding
GON Fund
Location Transaction Date Amount
Federal NPR
Benificary Fund
Location Transaction Date Amount
Federal NPR
Swiss Agency for Development and Cooperation
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 01-01-2016 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Humanitarian Assistance 5,727,356 USD
Sub Total Actual Commitment: 5,727,356 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 06-16-2016 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Humanitarian Assistance 2,034,834 USD
Actual Disbursement 12-15-2017 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Humanitarian Assistance 790,613 USD
Actual Disbursement 07-17-2018 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Humanitarian Assistance 1,635,349 USD
Actual Disbursement 02-18-2019 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Humanitarian Assistance 546,120 USD
Actual Disbursement 11-20-2019 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Humanitarian Assistance 554,703 USD
Sub Total Actual Disbursement: 5,561,619 USD
Planned Disbursement 05-10-2016 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Humanitarian Assistance 2,020,646 USD
Planned Disbursement 07-31-2017 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Humanitarian Assistance 1,383,892 USD
Planned Disbursement 08-31-2018 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Humanitarian Assistance 1,671,420 USD
Planned Disbursement 02-28-2019 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Humanitarian Assistance 551,550 USD
Planned Disbursement 12-31-2019 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Humanitarian Assistance 554,703 USD
Planned Disbursement 07-31-2020 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Humanitarian Assistance 229,950 USD
Sub Total Planned Disbursement: 6,412,161 USD
UNDISBURSED BALANCE: 165,737 USD
Progress Achieved

Progress Achieved: 


Key Problems: 


Steps Taken to solve the problem: 


Document

Open a PDF file of the doc attached Open.