TA 9457: Institutional Strengthening of the Nepal Rural Road Sector for Sustainable Development

Funding Information
(USD)
Total Actual Commitment:
1,000,000 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
955,877 USD
Total Planned Disbursements:
0 USD
Unallocated Disbursements:
44,123 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
adb@amp.org
Project Modified By:
adb@amp.org
Project Created On:
09/02/2019
Created in workspace:
ADB -Team
 
Identification
Project Title: 
TA 9457: Institutional Strengthening of the Nepal Rural Road Sector for Sustainable Development VALIDATED
ID: 
872387924003

IATI Identifier: 


Gender Marker: 


Climate Change Relevance: 


Status:  On-Going
Budget Head: 
Status Reason: 
Input: 

Outputs: 

Outcome:

Impact: 

Budget Type:
Off Budget

Treasury Type:


Humanitarian Aid: No

Planning

Date of Agreement:  01-03-2018
Date of effectiveness:  01-03-2018
Proposed Start Date:  01-03-2018
Actual Start Date:  01-03-2018
Planned Completion Date:  09-30-2019
Location
[NEPAL] 100.0%

X

Map

Show Map
National Plan
[National Development Plan (NDP)]   [Infrastructure Development Policy]   [Rural Infrastructure] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - ROAD TRANSPORTATION (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • Asian Development Bank

Counterpart Ministry : 
  • Ministry of Federal Affairs and Local Development 100.0 %

Executing Agency: 
  • Department of Local Infrastructure Development and Agricultural Roads 100.0 %

Implementing Agency: 
  • Department of Local Infrastructure Development and Agricultural Roads 100.0 %
Funding
Asian Development Bank
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 01-03-2018 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Sector Wide Approach 1,000,000 USD
Sub Total Actual Commitment: 1,000,000 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 03-15-2019 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Sector Wide Approach 70,481 USD
Actual Disbursement 07-15-2019 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Sector Wide Approach 70,481 USD
Actual Disbursement 07-20-2021 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Sector Wide Approach 714,440 USD
Actual Disbursement 11-15-2021 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Sector Wide Approach 8,938 USD
Actual Disbursement 03-15-2022 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Sector Wide Approach 43,502 USD
Actual Disbursement 07-15-2022 Technical Assistance (Standalone) Direct Payment No NORMAL CASE Sector Wide Approach 48,035 USD
Sub Total Actual Disbursement: 955,877 USD
Sub Total Planned Disbursement: 0 USD
UNDISBURSED BALANCE: 44,123 USD
Progress Achieved

Progress Achieved: 


Key Problems: 


Steps Taken to solve the problem: 


Document

Open a PDF file of the doc attached Open.