Rehabilitation of Facilities of Earthquake affected population (REAP)

Funding Information
(USD)
Total Actual Commitment:
5,478,433 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
6,169,859 USD
Total Planned Disbursements:
0 USD
Unallocated Disbursements:
-691,426 USD
TOTAL EXPENDITURES:
5,553,785 USD USD
Additional Information
Project Created By:
helvetassin@amp.org
Project Modified By:
helvetassin@amp.org
Project Created On:
12/06/2016
Created in workspace:
HELVETAS Swiss Intercooperation Nepal -Team
 
Identification
Project Title: 
Rehabilitation of Facilities of Earthquake affected population (REAP) VALIDATED
ID: 
8723830315904

IATI Identifier: 


Gender Marker: 


Climate Change Relevance: 


Status:  On-Going
Budget Head: 
Status Reason: 
Input: 

Outputs: 

Outcome:

Impact: 

Budget Type:
Off Budget

Treasury Type:


Humanitarian Aid: No

Planning

Date of Agreement:  08-01-2015
Date of effectiveness:  08-01-2015
Proposed Start Date:  08-01-2015
Actual Start Date:  08-01-2015
Planned Completion Date:  06-30-2018
Location
[Bagmati] [Sindhupalchok (Chautara)] 100.0%

X

Map

Show Map
National Plan
[National Development Plan (NDP)]   [Infrastructure Development Policy]   [Building, Housing and Urban Development] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - EARTHQUAKE RECONSTRUCTION (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • HELVETAS Switzerland

Counterpart Ministry : 
  • Ministry of Urban Development 100.0 %

Executing Agency: 
  • HELVETAS Swiss Intercooperation Nepal 100.0 %

Implementing Agency: 
  • Non Governmental Organisations 100.0 %
Funding
HELVETAS Switzerland
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 08-01-2015 Grant Aid Direct Payment No NORMAL CASE Project Support 5,478,433 USD
Sub Total Actual Commitment: 5,478,433 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 12-31-2015 Grant Aid Direct Payment No NORMAL CASE Project Support 79,491 USD
Actual Disbursement 06-30-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 351,517 USD
Actual Disbursement 12-31-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 616,075 USD
Actual Disbursement 12-31-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 2,516,733 USD
Actual Disbursement 12-31-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 1,707,830 USD
Actual Disbursement 06-30-2019 Grant Aid Direct Payment No NORMAL CASE Project Support 898,212 USD
Sub Total Actual Disbursement: 6,169,859 USD
Sub Total Planned Disbursement: 0 USD
UNDISBURSED BALANCE: -691,426 USD
Expenditure 12-31-2015 Grant Aid Direct Payment No NORMAL CASE Project Support 79,491 USD
Expenditure 06-30-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 351,517 USD
Expenditure 12-31-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 2,516,733 USD
Expenditure 12-31-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 1,707,830 USD
Expenditure 06-30-2019 Grant Aid Direct Payment No NORMAL CASE Project Support 898,212 USD
Progress Achieved

Progress Achieved: 


Key Problems: 


Steps Taken to solve the problem: 


Document

Open a PDF file of the doc attached Open.