Reconstruction and upgrading of electricity supply in EQ districts

Funding Information
(USD)
Total Actual Commitment:
5,473,500 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
130,995 USD
Total Planned Disbursements:
0 USD
Unallocated Disbursements:
5,342,505 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
germany@amp.org
Project Modified By:
germany@amp.org
Project Created On:
01/04/2017
Created in workspace:
German Development Cooperation -Team
 
Identification
Project Title: 
Reconstruction and upgrading of electricity supply in EQ districts VALIDATED
ID: 
872389516231

IATI Identifier: 


Gender Marker: 


Climate Change Relevance: 


Status:  On-Going
Budget Head: 
Status Reason: 
Input: 

Financial assistance for extension, reconstruction and upgrading of electricity distribution system in Rasuwa and Nuwakot districts


Outputs: 

Electricity distribution infrastructure will be extended, reconstructed and upgraded in the districts


Outcome:

100 % of the households in the districts get reliable electricity supply


Impact: 

Budget Type:
On Budget

Treasury Type:


Humanitarian Aid: No

Planning

Date of Agreement: 
Date of effectiveness: 
Proposed Start Date: 
Actual Start Date: 
Planned Completion Date: 
Location
[Bagmati] [Dhading (Dhading Besi)] 33.0%

[Bagmati] [Rasuwa (Dhunche)] 33.0%

[Bagmati] [Nuwakot (Bidur)] 34.0%

X

Map

Show Map
National Plan
[Infrastructure Development Policy]   [Water Resources]   [Hydro Electricity] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - ENERGY (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • German Development Cooperation (KfW)

Counterpart Ministry : 
  • Ministry of Energy 100.0 %

Executing Agency: 
  • Nepal Electricity Authority 100.0 %

Implementing Agency: 
  • Nepal Electricity Authority 100.0 %
Funding
German Development Cooperation (KfW)
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 12-28-2015 Grant Aid Direct Payment No NORMAL CASE Humanitarian Assistance 5,473,500 USD
Sub Total Actual Commitment: 5,473,500 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 12-31-2017 Grant Aid Direct Payment No NORMAL CASE Humanitarian Assistance 61,195 USD
Actual Disbursement 12-31-2018 Grant Aid Direct Payment No NORMAL CASE Humanitarian Assistance 69,800 USD
Sub Total Actual Disbursement: 130,995 USD
Sub Total Planned Disbursement: 0 USD
UNDISBURSED BALANCE: 5,342,505 USD
Progress Achieved

Progress Achieved: 


Key Problems: 


Steps Taken to solve the problem: 


Document

Open a PDF file of the doc attached Open.