Tatopani Frontier Inspection Station Project

Funding Information
(USD)
Total Actual Commitment:
13,637,514 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
13,718,628 USD
Total Planned Disbursements:
0 USD
Unallocated Disbursements:
-81,114 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
china@amp.org
Project Modified By:
atl@mof.gov.np
Project Created On:
06/21/2011
Created in workspace:
China -Team
 
Identification
Project Title: 
Tatopani Frontier Inspection Station Project VALIDATED
ID: 
87238115535

IATI Identifier: 


Gender Marker: 


Climate Change Relevance: 


Status:  New
Budget Head:  305 
Status Reason: 
Input: 

Outputs: 

Outcome:

Impact: 

Budget Type:
Off Budget

Treasury Type:


Humanitarian Aid: No

Planning

Date of Agreement:  09-10-2009
Date of effectiveness:  09-10-2009
Proposed Start Date: 
Actual Start Date: 
Planned Completion Date: 
Location
[NEPAL] 100.0%

X

Map

Show Map
National Plan
Sectors

PRIMARY SECTORS
Nepal Sector Classification - COMMERCE (100.0)%

Nepal Functional Coding - ECONOMIC AFFAIRS (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • China

Counterpart Ministry : 
  • Ministry of Finance 100.0 %

Executing Agency: 
  • Ministry of Supplies 100.0 %

Implementing Agency: 
  • Ministry of Supplies 100.0 %
Funding
China
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 05-17-2012 Grant Aid Direct Payment No NORMAL CASE Project Support 13,637,514 USD
Sub Total Actual Commitment: 13,637,514 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 05-17-2012 Grant Aid Direct Payment No NORMAL CASE Project Support 6,819,548 USD
Actual Disbursement 12-20-2012 Grant Aid Direct Payment No NORMAL CASE Project Support 5,519,819 USD
Actual Disbursement 11-21-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 1,379,261 USD
Sub Total Actual Disbursement: 13,718,628 USD
Sub Total Planned Disbursement: 0 USD
UNDISBURSED BALANCE: -81,114 USD
Progress Achieved

Progress Achieved: 


Key Problems: 


Steps Taken to solve the problem: 


Document

Open a PDF file of the doc attached Open.