Integrated Urban Development Project (Nepal)

Funding Information
(USD)
Total Actual Commitment:
56,800,000 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
43,822,135 USD
Total Planned Disbursements:
12,982,000 USD
Unallocated Disbursements:
12,977,865 USD
TOTAL EXPENDITURES:
0 USD USD
Additional Information
Project Created By:
atl@mof.gov.np
Project Modified By:

Project Created On:
07/02/2021
Created in workspace:
IECCD Workspace -Team
 
Identification
Project Title: 
Integrated Urban Development Project (Nepal) VALIDATED
ID: 
87238312320

IATI Identifier: 


Gender Marker: 
Neutral

Climate Change Relevance: 
Neutral

Status:  On-Going
Budget Head:  347320 501169 
Status Reason: 

 


Input: 
  • Municipal infrastructure improvement
  • Community development and GESI strengthening
  • Project management and administration

 


Outputs: 

 


Outcome:

Population in project municipalities have inclusively better access to improved municipal infrastructure and services.


Impact: 

Improved urban environment in the municipalities of Dharan, Janakpur, Nepalgunj and Siddharthanagar.



Budget Type:
On Budget

Treasury Type:


Humanitarian Aid: No

Planning

Date of Agreement:  05-08-2012
Date of effectiveness:  07-04-2012
Proposed Start Date:  01-01-2012
Actual Start Date:  07-04-2012
Planned Completion Date:  06-30-2017
Extension Date 1:  07-04-2012
Location
[Bheri] [Banke (Nepalgunj)] 25.0%

[Koshi ] [Sunsari (Inaruwa)] 25.0%

[Lumbini ] [Rupandehi (Bhairahawa)] 25.0%

[Janakpur] [Dhanusa (Janakpur)] 25.0%

X

Map

Show Map
National Plan
[National Development Plan (NDP)]   [Infrastructure Development Policy]   [Building, Housing and Urban Development] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - URBAN DEVELOPMENT (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • Asian Development Bank

Counterpart Ministry : 
  • Ministry of Finance - Investments in Public Enterprises 50.0 %
  • Ministry of Physical Infrastructure and Transport 50.0 %

Executing Agency: 
  • Ministry of Finance 50.0 %
  • Ministry of Physical Infrastructure and Transport 50.0 %

Implementing Agency: 
  • Department of Urban Development & Building Construction 100.0 %
Funding
GON Fund
Location Transaction Date Amount
Federal NPR
Benificary Fund
Location Transaction Date Amount
Federal NPR
Asian Development Bank
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 05-08-2012 Grant Aid Reimbursable No NORMAL CASE Project Support 12,000,000 USD
Actual Commitment 05-08-2012 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 44,800,000 USD
Sub Total Actual Commitment: 56,800,000 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 03-15-2013 Grant Aid Reimbursable No NORMAL CASE Project Support 300,000 USD
Actual Disbursement 07-15-2013 Grant Aid Reimbursable No NORMAL CASE Project Support 311,195 USD
Actual Disbursement 11-15-2013 Grant Aid Reimbursable No NORMAL CASE Project Support 522,845 USD
Actual Disbursement 03-15-2014 Grant Aid Reimbursable No NORMAL CASE Project Support 236,765 USD
Actual Disbursement 07-15-2014 Grant Aid Reimbursable No NORMAL CASE Project Support 705,885 USD
Actual Disbursement 03-15-2015 Grant Aid Reimbursable No NORMAL CASE Project Support 312,583 USD
Actual Disbursement 07-15-2015 Grant Aid Reimbursable No NORMAL CASE Project Support 488,062 USD
Actual Disbursement 07-15-2015 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 1,036,235 USD
Actual Disbursement 11-15-2015 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 3,625,594 USD
Actual Disbursement 11-15-2015 Grant Aid Reimbursable No NORMAL CASE Project Support 904,494 USD
Actual Disbursement 03-15-2016 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 2,003,104 USD
Actual Disbursement 03-15-2016 Grant Aid Reimbursable No NORMAL CASE Project Support 127,763 USD
Actual Disbursement 07-15-2016 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 5,083,736 USD
Actual Disbursement 07-15-2016 Grant Aid Reimbursable No NORMAL CASE Project Support 232,667 USD
Actual Disbursement 11-30-2016 Grant Aid Reimbursable No NORMAL CASE Project Support 565,629 USD
Actual Disbursement 11-30-2016 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 3,085,496 USD
Actual Disbursement 03-31-2017 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 1,193,972 USD
Actual Disbursement 03-31-2017 Grant Aid Reimbursable No NORMAL CASE Project Support 148,981 USD
Actual Disbursement 07-15-2017 Grant Aid Reimbursable No NORMAL CASE Project Support 564,287 USD
Actual Disbursement 07-15-2017 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 4,102,894 USD
Actual Disbursement 11-15-2017 Grant Aid Reimbursable No NORMAL CASE Project Support 582,671 USD
Actual Disbursement 11-15-2017 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 2,069,900 USD
Actual Disbursement 03-15-2018 Grant Aid Reimbursable No NORMAL CASE Project Support 203,762 USD
Actual Disbursement 03-15-2018 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 1,091,391 USD
Actual Disbursement 07-15-2018 Grant Aid Reimbursable No NORMAL CASE Project Support 266,219 USD
Actual Disbursement 07-15-2018 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 1,711,914 USD
Actual Disbursement 11-15-2018 Grant Aid Reimbursable No NORMAL CASE Project Support 621,968 USD
Actual Disbursement 11-15-2018 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 2,520,219 USD
Actual Disbursement 03-15-2019 Grant Aid Reimbursable No NORMAL CASE Project Support 202,723 USD
Actual Disbursement 03-15-2019 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 3,088,194 USD
Actual Disbursement 07-15-2019 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 1,770,932 USD
Actual Disbursement 07-15-2019 Grant Aid Reimbursable No NORMAL CASE Project Support 212,965 USD
Actual Disbursement 11-15-2019 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 453,115 USD
Actual Disbursement 03-13-2020 Grant Aid Reimbursable No NORMAL CASE Project Support 271,624 USD
Actual Disbursement 03-13-2020 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 712,688 USD
Actual Disbursement 07-15-2020 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 1,641,773 USD
Actual Disbursement 10-30-2020 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 182,134 USD
Actual Disbursement 11-15-2020 Grant Aid Reimbursable No NORMAL CASE Project Support 665,756 USD
Sub Total Actual Disbursement: 43,822,135 USD
Planned Disbursement 11-15-2015 Grant Aid Reimbursable No NORMAL CASE Project Support 1,712,000 USD
Planned Disbursement 11-15-2015 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 4,270,000 USD
Planned Disbursement 07-15-2016 Grant Aid Reimbursable No NORMAL CASE Project Support 1,000,000 USD
Planned Disbursement 07-15-2016 Concessional Loan Assistance Reimbursable No NORMAL CASE Project Support 6,000,000 USD
Sub Total Planned Disbursement: 12,982,000 USD
UNDISBURSED BALANCE: 12,977,865 USD
Progress Achieved

Progress Achieved: 

 


Key Problems: 

 


Steps Taken to solve the problem: 

 


Document

Open a PDF file of the doc attached Open.