Nepal Nutrition Intervention Project-Sarlahi

Funding Information
(USD)
Total Actual Commitment:
4,588,556 USD
Total Planned Commitment:
0 USD
Total Actual Disbursements:
4,735,356 USD
Total Planned Disbursements:
0 USD
Unallocated Disbursements:
-146,800 USD
TOTAL EXPENDITURES:
4,570,291 USD USD
Additional Information
Project Created By:
jhu@amp.org
Project Modified By:
jhu@amp.org
Project Created On:
06/06/2014
Created in workspace:
Johns Hopkins University -Team
 
Identification
Project Title: 
Nepal Nutrition Intervention Project-Sarlahi VALIDATED
ID: 
872385118629

IATI Identifier: 


Gender Marker: 


Climate Change Relevance: 


Status:  On-Going
Budget Head:  340 
Status Reason: 
Input: 

Public Health Research Studies


Outputs: 

Public Health Research Results


Outcome:

Results used as basis for government policy formulation and program development


Impact: 

Improvement in health and survival indicators for women and children



Budget Type:
Off Budget

Treasury Type:


Humanitarian Aid: Yes

Planning

Date of Agreement:  07-11-2014
Date of effectiveness:  07-11-2014
Proposed Start Date: 
Actual Start Date: 
Planned Completion Date:  07-11-2019
Location
[Janakpur] [Sarlahi (Malangwa)] 100.0%

X

Map

Show Map
National Plan
[National Development Plan (NDP)]   [Social Development Policy]   [Health and Nutrition] 100.0%
Sectors

PRIMARY SECTORS
Nepal Sector Classification - HEALTH (100.0)%


Implementing/Executing Agencies

Donor Organization: 
  • Johns Hopkins University

Counterpart Ministry : 
  • Ministry of Women, Children & Social Welfare 100.0 %

Executing Agency: 
  • Johns Hopkins University 100.0 %

Implementing Agency: 
  • Non Governmental Organisations 100.0 %
Funding
Johns Hopkins University
Transaction Type Transaction Date Type Of Assistance Mode Of Payment Post Earthquake Assistance Aid Type Financing Instrument Amount
Actual Commitment 07-01-2014 Grant Aid Direct Payment No NORMAL CASE Project Support 4,588,556 USD
Sub Total Actual Commitment: 4,588,556 USD
Sub Total Planned Commitment: 0 USD
Actual Disbursement 12-31-2014 Grant Aid Direct Payment No NORMAL CASE Project Support 801,779 USD
Actual Disbursement 06-30-2015 Grant Aid Direct Payment No NORMAL CASE Project Support 683,053 USD
Actual Disbursement 12-31-2015 Grant Aid Direct Payment No NORMAL CASE Project Support 858,543 USD
Actual Disbursement 06-30-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 649,975 USD
Actual Disbursement 12-30-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 843,448 USD
Actual Disbursement 06-30-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 451,161 USD
Actual Disbursement 12-30-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 129,548 USD
Actual Disbursement 06-29-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 153,666 USD
Actual Disbursement 12-19-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 164,185 USD
Sub Total Actual Disbursement: 4,735,356 USD
Sub Total Planned Disbursement: 0 USD
UNDISBURSED BALANCE: -146,800 USD
Expenditure 12-31-2014 Grant Aid Direct Payment No NORMAL CASE Project Support 727,317 USD
Expenditure 06-30-2015 Grant Aid Direct Payment No NORMAL CASE Project Support 689,084 USD
Expenditure 12-31-2015 Grant Aid Direct Payment No NORMAL CASE Project Support 854,117 USD
Expenditure 06-30-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 700,129 USD
Expenditure 12-30-2016 Grant Aid Direct Payment No NORMAL CASE Project Support 723,797 USD
Expenditure 06-30-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 393,210 USD
Expenditure 12-30-2017 Grant Aid Direct Payment No NORMAL CASE Project Support 129,668 USD
Expenditure 06-29-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 145,096 USD
Expenditure 12-19-2018 Grant Aid Direct Payment No NORMAL CASE Project Support 207,873 USD
Progress Achieved

Progress Achieved: 


Key Problems: 


Steps Taken to solve the problem: 


Document